The declaration for the conversion of the Ptolemaida V powerfulness works from a lignite-fired installation to a earthy state unit, with a fund of 420 cardinal euros, has been awarded by PPC to Terna, a subsidiary of the GEK Terna Group.
According to the applicable Environmental Impact Assessment, the task will beryllium implemented successful two phases. During the archetypal phase, the works will beryllium converted into an unfastened rhythm state turbine (OCGT) unit, done the installation of a state turbine (GT) with a gross nominal capableness of 294.95 MWe and a gross ratio of 39.77% under section notation conditions. In unfastened rhythm operation, the unit will present a nett capableness of 292.95 MWe, with a nett ratio of 39.5%.
In the 2nd phase, the conversion into a combined rhythm state turbine (CCGT) unit will beryllium completed, with the installation of a vigor betterment steam generator (HRSG), which will beryllium connected to the state turbine exhaust stack astatine its base. The generated steam will provender a steam turbine (ST) with a nominal capableness of 144.05 MWe, to beryllium installed adjacent within the turbine hall.
Under combined rhythm operation, the works will person a gross nominal capableness of 438.60 MWe and a gross ratio of 59.60%, while nett capableness will scope 430 MWe, with an estimated nett ratio of 58.44% under section notation conditions. The timeline foresees the commencement of first-phase works successful the coming August, with the unit entering trial cognition successful October 2027 and commercialized cognition pursuing successful December of the aforesaid year. As for the 2nd phase, works are scheduled to statesman successful January 2028 and beryllium completed by December 2029.








Greek (GR) ·
English (US) ·